Roadworks: Main street and Cambridge Road footpath upgrade

The advance warning signs are up for the Main Street/Cambridge Road Footpath Upgrade.

Starting 8th March, the contractors expect it will take 10 weeks.

The work starts at Egremont Road Junction. You will see a Section 5 “To be

confirmed”. This is on hold while County Council work out the Greenways (Cycle path) options for the Portway. We will try to address concerns on line but please feel free to email the Parish Clerk

 

Dates:

Section

Location

Date

1

Working back from Egremont Road to opposite Kesters Close

09/03/21- 16/03/21

2

Working back from opposite Kesters Close to the Bin Brook Culvert by 8 Main Street

16/03/21 – 24/03/21

3A

Bend near St Mary’s Church

17/03/21 – 30/03/21

3

Bin Brook Culvert to approaching St Mary’s Church Bend

30/03/21 – 14/04/21

4

The Pastures to The Blue Lion

14/04/21 – 26/04/21

5*

Pastures to end of Village, south

TBC

6

Egremont Road to Limes Road

16/04/21 – 24/04/21

If you would like to see the drawing for the work, they are linked : 1 , 2 , 3, 4